
By Matt de Simone
Progress continues at a steady pace on two of Botetourt County’s major capital projects, with Capital Projects Manager Rich Evans offering an encouraging update to the Botetourt County Board of Supervisors during its March 24 meeting.
Evans reported that construction of the Botetourt County Circuit Courthouse is “moving along well,” with visible progress taking shape at the site along Route 220.
A crane that has dominated the skyline in recent months is expected to be removed within weeks as steel erection nears completion. Crews have also been installing stone veneer along the Route 220 retaining wall, significantly improving the site’s appearance.

“I hope all of you would agree it’s looking a lot better,” Evans said.
Work is also underway on the courthouse’s prominent front columns, with concrete footers and piers already poured and steel installation now in progress. Meanwhile, the lower parking lot is being brought to grade, including installation of infrastructure for future lighting.
A major milestone is expected in mid- to late May, when the building’s cupola is installed. Evans noted the occasion will be marked by a traditional “topping out” ceremony, calling it “a pretty significant milestone in a project.”
Despite minor setbacks involving steel welding, which have since been resolved, the project remains on track. Evans highlighted a notable financial achievement as well, stating that the county has saved more than $250,000 through its direct purchase program.
“That’s a lot of work… but it’s certainly worth the cost,” he said, thanking county staff for their efforts.

File photo
Looking ahead, Evans said permanent power is expected to be connected to the courthouse around November, with substantial completion of the steel structure anticipated by September 2027.
Supervisors also received an update on construction at the Read Mountain Fire Station 7 and the county’s 911 call center, where Evans described progress as moving “at a very accelerated rate.”
At the site, crews have largely completed exterior work on the radio shop, including metal siding and brick veneer. Interior work is nearing completion, with drywall installed and painting underway. Evans said the space could be ready for occupancy within weeks.
Mechanical, electrical and plumbing systems are also progressing, with HVAC systems and a large exhaust fan already in place.
Construction continues on the main fire station and 911 facility, where walls are being framed and concrete decking installed. However, Evans noted that unexpected rock removal has caused some delays in portions of the project.
Even so, the overall pace has remained strong, with crews working at least six days a week.
Evans also reminded the public to use caution when traveling near the construction site, particularly along the access road shared with a nearby church.
“There are a lot of workers and heavy machinery,” he said. “Please maintain safe speeds.”
Board members thanked Evans for the update and praised the progress being made on both projects, which remain among the county’s most significant infrastructure investments.


